Smart terminals · Phones and wearables
Changeovers are frequent; records have to keep up
The Huizhou site runs phones and wearables together, in small lots with frequent model changes. A changeover puts dozens of reels at the line side, and a complaint requires tracing a single unit back to a reel.
Small orders and frequent changeovers outrun paper: kitting, loading and test move into the system.
Customer background
High mix, low volume, several changeovers a day
Two lines share the warehouse and front-end equipment. Models follow the order book, and changing lines several times a day is normal. Customers differ in how much detail they want in shipping documents: some take a batch summary, some want it per unit.
Before the rollout, kit quantities came from the team leader's experience and issue slips carried numbers but no reel IDs. Test results were printed at the station and entered again into a summary, which is where most errors came from.
Problems
Three problems that come with changeovers
The more often the line changes, the harder paper is to keep up with. The gaps showed up in kitting, traceability granularity and test data.
-
01
Kitting runs on experience and piles up at the line
On a model change the team leader estimates quantities and the warehouse issues by number. The surplus sits at the line side until the next changeover, when it has to be cleared again.
-
02
Traceability stops at the batch, not the reel
Several batches of one part number coexist. A quality issue can only be fenced off by batch; narrowing it to a reel means going back to the issue slips and comparing times.
-
03
Test data is copied by hand, then entered again
Results are printed at the station and summarised in a spreadsheet. Copy errors and missing rows surface during the summary, and fixing them takes as long as the test.
-
04
Paste and stencil status on paper
Warm-up is written on the jar and stencil counts in a notebook; on a busy changeover paste goes on early and stencils run past their count.
Scope
Four stages, six module groups
Warehouse and SMT first to prove the changeover flow, then DIP, test and assembly.
Process stage
Modules in use
Approach
Kitting moves ahead of the changeover
Much of a changeover is spent finding and counting material. Move both ahead into the warehouse and the system, and the line side only verifies.
-
01
Kit lists issued before the changeover
The work order and placement table generate the kit list; the warehouse picks, scans and issues ahead of time, and the line side only verifies.
-
02
Loading scans against part and feeder
Part number, batch and slot must agree. Substitutes are validated against maintained pairings instead of verbal approval.
-
03
Reel-level traceability from loading timestamps
The loading scan leaves a timestamp; combined with the station time window it identifies the reel and batch behind a given board.
-
04
Test results post back on their own
Tester output writes back to MES against the SN. Nothing is printed at the station and nothing is entered twice.
-
05
Paste cannot be issued before warm-up
Paste is coded by batch and warm-up is timed by the system; issue is blocked before it completes, and top-ups are recorded.
-
06
Stencil scanned for use count
The stencil code carries model and open date; scanning at the line checks model, count and cleaning state, with an alarm past the limit.
Results
Useful at both ends: complaints and shipment
No percentage gains, only the questions the system can answer.
-
No surplus left at the line after a changeover
Kits name the reels to pick, so line-side stock stays small and clearing goes faster.
-
A complaint can be traced to the reel
By SN you get material, stations and test records; by reel you get where it went. One export covers it.
-
Shipment checks have something to check against
Carton IDs are bound to SNs in packaging, so the packing list matches the physical goods: no missing units, no mixed cartons.
-
Consumable and tooling status is queryable
Paste warm-up, stencil counts and cleaning records are in the system, ready for an audit.
More cases
Similar projects
Scope varies — match it against the process stages in your own plant.
Similar projects
High mix starts with kitting
If changeover time goes into finding and counting material, start with the feeder placement table and kit lists.
- Phone
- 134 1205 3770
- chengzhi780@bczktech.cn
- Address
- Building 8, Room 303, Yilisheng Industrial Park, 602 Fengtang Avenue, Tangwei Community, Fuhai Street, Bao'an District, Shenzhen
Shenzhen Baichuan Zhike Technology Co., Ltd. · Since 2015 , serving electronics manufacturers across handsets, tablets, automotive electronics, FPC, WiFi modules, energy storage and more.