Electronics manufacturing · Boards and finished units

Changeover time saved before the changeover

Orders are small and varied, and SMT changes over several times a day. The project did not touch the machine cycle; it took the material and checks around a changeover and moved them: kitting is done in the warehouse, the line only verifies.

High-mix, low-volume: material reaches the line before the changeover.

Client background

Several changeovers a day, half of it spent finding material

Many models, few units per batch, and one mounter runs several products a day. Little of the changeover goes to setting the machine; most goes to finding material, counting and checking station by station.

Before go-live, kitting was estimated from experience and split again at the line; loading compared reels against a paper feeder table station by station, and changeovers were where it slipped; a wrong part surfaced at AOI or test, and a whole batch went to rework.

The problems

The changeover bottleneck is not the mounter

The machine cycle is fixed; what can be compressed is the preparation around a changeover.

  1. 01

    Finding and counting eat the changeover

    Dozens of reels wait at the line, and finding, counting and refilling all fall into the same window.

  2. 02

    Wrong parts rely on a second pair of eyes

    Loading compares against a paper feeder table station by station; changeovers slip, and a wrong part surfaces at AOI or test.

  3. 03

    Changeover checks leave no record

    Whether the check was done, and how many stations were covered, rests on the shift's memory.

Scope

Warehousing, four stages, equipment integration

Warehousing and kitting are the focus; the four stages and equipment data join on the same work order.

Process stage

  • SMT
  • DIP
  • Test
  • Assembly

Modules in use

  • Smart warehousing
  • Loading error-proofing
  • Material traceability
  • Process traceability
  • Test parameter traceability
  • Equipment integration

View all 15 modules

Approach

Kit earlier, verify later

What can be done ahead moves before the changeover; what must be done on the floor shrinks to one scan.

  1. 01

    Kits generated from the feeder table

    Before a changeover the material list is calculated from the work order and feeder table; the warehouse picks by location and delivers a complete set.

  2. 02

    Loading verified by scan

    Scan the reel, the station and the feeder, compare with the table; a mismatch alarms and stops the line.

  3. 03

    Changeovers check differences only

    For the same product, only changed stations are checked; for a new product, all stations are checked, and the result is kept.

  4. 04

    Equipment data posted back

    Printer, SPI, mounter, reflow oven and AOI data are filed by work order; the counter relabels after counting.

  5. 05

    One pass chain across four stages

    SMT, DIP, test and assembly share the work order and SN, and later stages inherit earlier data.

Results

A changeover is now checking and setting

Questions the system now answers: which reels this changeover needs, where a wrong part was blocked, how many stations were checked.

  1. Kitting has a basis

    Kits come from the feeder table instead of an estimated quantity.

  2. Wrong parts blocked before placement

    A failed check stops the line, without waiting for AOI.

  3. Changeover checks leave a record

    Which stations, by whom and when — all retrievable.

  4. Later stages inherit the data

    DIP, test and assembly reuse the earlier work order and material records.

Fast changeover

Many changeovers a day is a reason to change kitting

Starting from the feeder table and the BOM, kits can be generated before each changeover.

Address
Building 8, Room 303, Yilisheng Industrial Park, 602 Fengtang Avenue, Tangwei Community, Fuhai Street, Bao'an District, Shenzhen

Shenzhen Baichuan Zhike Technology Co., Ltd. · Since 2015 , serving electronics manufacturers across handsets, tablets, automotive electronics, FPC, WiFi modules, energy storage and more.

Used for this conversation only; never shared externally. By submitting you agree to be contacted about this request.

Questions?